Telus is withdrawing from its partnership with Westbank to co-develop two planned AI data centres in Vancouver.
Key facts
- In May, Telus announced a joint initiative with the federal government and Westbank to build a “sovereign AI factory cluster” that included two Vancouver facilities.
- The two Vancouver projects were planned for 150 West Georgia St. (a new 10-storey AI data centre building) and 111 East 5th Ave. (the M3 office building in Mount Pleasant to be converted for AI use).
- Telus said its Kamloops AI data-centre expansion to 20 MW by the end of 2028 will proceed.
- Telus said it is evaluating new partners and sites for the long-term expansion of its sovereign compute capabilities in B.C.
The company gave no reason for its decision and said it will share more about its AI strategy in the coming months. Westbank, meanwhile, says both Vancouver projects will continue with a new partner that has not yet been publicly announced.
Planned Vancouver sites and timelines
In May, Telus announced a joint initiative with the federal government and Westbank to create a “sovereign AI factory cluster,” including two Vancouver facilities.
One was planned for 150 West Georgia St., where a new 10-storey AI data-centre building was proposed. The other would convert the M3 office building at 111 East 5th Ave. in Mount Pleasant for AI use.
The converted Mount Pleasant facility had been expected to open at the end of 2026. The downtown new-build project was to come online in 2029.
A Westbank spokesperson said: “We can confirm that Telus is no longer a partner on the two Vancouver projects but we are proceeding with a new partnership.”
Mount Pleasant rezoning process
The Mount Pleasant proposal remains before the City of Vancouver. The city pulled its rezoning application from the July public-hearing agenda, then scheduled an additional public question-and-answer period from Dec. 2 to 15.
That process now continues without Telus as Westbank’s co-development partner, while the developer has not named the company that will take Telus’s place.
Kamloops data centre expansion
Telus says it will proceed with the expansion of its Kamloops AI data centre to 20 MW by the end of 2028.
The company is also evaluating new partners and locations for the long-term expansion of its sovereign compute capabilities in British Columbia.
“TELUS remains committed to advancing Canada’s digital sovereignty,” a company spokesperson said, describing its goal as building secure, sustainable, high-performance computing infrastructure.
Federal memorandum of understanding terms not finalized
According to The Globe and Mail, Telus had signed a memorandum of understanding with the federal government to support its data-centre initiatives, though the terms had not been finalized.
What we don't know yet
- Telus has not provided an explanation for why it decided not to proceed with the two Vancouver projects.
- A new partner to replace Telus on the two Vancouver projects has not yet been publicly announced.
- Details about Telus’s updated AI strategy have not yet been released, with the company saying it will share more in the coming months.
- The terms of the memorandum of understanding between Telus and the federal government for the data-centre initiatives have not been finalized.
How outlets covered it
- Western Investor — “Telus backs away from plans for two AI data centres in Vancouver: reports”, Nov. 16, 2026. By Catherine Skrzypinski. Quoted real estate developer Westbank Corp; Daily Hive; Then-CEO Darren Entwistle. Not in the other reports here: a $2-billion revenue target across Telus Digital and Telus Business Solutions by 2028.
- The Province (Postmedia) — “Telus drops its involvement in two planned AI data centres in Vancouver”, Nov. 16, 2026. By Yvonne Lau. Led with Telus withdrawing from its Vancouver data-centre partnership. Quoted a spokesperson; Telus.
- MobileSyrup — “Telus ditching Westbank's two Vancouver AI data centre projects”, Nov. 16, 2026. By Kenneth Chan. Led with Telus ending its Westbank partnership while the two projects continue. Quoted a Westbank spokesperson. Not in the other reports here: the downtown site’s integration with Creative Energy’s steam plant.
- The Globe and Mail (The Woodbridge Company) — “Telus pulls out of two planned Vancouver AI data centres”, Nov. 16, 2026. By Joe Castaldo and Irene Galea. Quoted spokesperson Richard Gilhooley; a source familiar with the matter; a spokesperson for Mr. Solomon’s office.
Reader-funded. No ads. No paywall.
The Canada Report is independent, reader-funded Canadian news — no advertisers, nothing behind a paywall, kept free for everyone. If you value it, you can help keep it that way.
Support The Canada Report →How we sourced this story
| Most key facts come from statements by Telus, Westbank and City of Vancouver, as reported by 4 news outlets. Outlets repeating the same statements do not confirm them independently. |
10 key facts · 0 independently corroborated · 9 from statements or releases · none disputed
Why some reports were counted once
MobileSyrup and Daily Hive — the same report, published near-identically, counted once.
Allegations described here are not proven in court unless stated.
Also used
- Telus no longer a partner in Westbank's two Vancouver AI data centre projects — Daily Hive, Nov. 14, 2026
How we put this together: we compare reporting from the outlets above, draft with the help of AI tools, and an editor checks every story before it's published. Our methodology.