Sourced from 3 news outlets · most facts from statements · no points in dispute. How we sourced this
Calgary’s replacement Bearspaw feeder main is fully built and connected to the city’s water system, moving a high-stakes infrastructure project into its commissioning phase.
Key facts
- Calgary says the replacement Bearspaw feeder main is fully built and connected to the city’s water system, and the project has moved into commissioning steps.
- Stage 4 water restrictions have been in place since Nov. 4, and Calgary expects them to be lifted in about a week.
- Before the new feeder main can be operated, it must be filled, pressurized, pressure tested, cleaned and flushed, and then pass water-quality testing.
- Calgary will refill the old Bearspaw feeder main over about five days, after which water samples will be taken for testing before the system is switched over.
Read the original document: City of Calgary, linked by CBC News.
Stage 4 water restrictions, in place since Nov. 4, are expected to be lifted in about a week if the remaining testing and system steps proceed as planned. Mayor Jeromy Farkas called the milestone a generational effort, saying: “And by the end of this year, we’ve landed on the moon, and now we’ve got to bring it home.”
Bearspaw Feeder Main Commissioning Steps
The new feeder main cannot yet be put into operation. It must first be filled and pressurized, then pressure tested, cleaned and flushed before passing water-quality testing.
The switch to the new feeder main comes after months of water-conservation measures that followed the Bearspaw break, including the high usage and stored reserves detailed in The Canada Report’s coverage of Calgary water usage remaining high after the major main break. Once the old line is refilled, crews will take samples to confirm the system is ready for service.
Calgary will also refill the old Bearspaw feeder main over roughly five days. Water samples will then be taken for testing before the system is switched over.
The work follows two failures of the feeder main: a rupture on June 5, 2024, and a second failure at the end of 2025. The $381-million replacement project began last January.
Risk of Failure in the Old Bearspaw Feeder Main
“We know the old pipe is in poor condition, and it’s still at risk of a break until the new feeder main is in service later in December,” Chief Operating Officer Michael Thompson said, adding that the refilling process will be carried out slowly and under constant monitoring.
Bearspaw Replacement Construction Details and Costs
According to LiveWire Calgary, Thompson said the replacement spans roughly 6.5 kilometres and is slightly ahead of schedule. About two-thirds of the line was installed through microtunneling, with the remaining third built through open-cut construction.
LiveWire Calgary also reported that Thompson said the city will disclose the project’s final cost once the work is complete and bills have been received.
What we don't know yet
- It has not yet been confirmed whether the new feeder main will pass water-quality testing and complete the remaining steps required before it is fully operated.
- It has not yet been confirmed whether Calgary will actually lift Stage 4 water restrictions late next week, despite the expectation that it will happen in about a week.
- The final total cost of the project has not yet been tallied and released to residents.
How outlets covered it
- CBC News (CBC/Radio-Canada) — “Construction complete on fast-tracked replacement for troubled Bearspaw feeder main”, Nov. 26, 2026. By Andrew Jeffrey. Quoted Mayor Jeromy Farkas. Not in the other reports here: the named neighbouring communities under Stage 4 restrictions.
- Calgary Herald (Postmedia) — “Construction on Bearspaw South feeder main substantially complete, restrictions to lift next week”, Nov. 26, 2026. By Scott Strasser. Quoted Michael Thompson. Not in the other reports here: the line supplying roughly 60 per cent of Calgary’s treated water; the June 5, 2024 first rupture and resulting summer restrictions.
- LiveWire Calgary — “Construction on the Bearspaw South replacement line is complete”, Nov. 26, 2026. By Darren Krause. Quoted Chief Operating Officer Michael Thompson; Mayor Jeromy Farkas. Not in the other reports here: the roughly 6.5-kilometre pipe section; the microtunneling construction route and share of the project.
Reader-funded. No ads. No paywall.
The Canada Report is independent, reader-funded Canadian news — no advertisers, nothing behind a paywall, kept free for everyone. If you value it, you can help keep it that way.
Support The Canada Report →How we sourced this story
| Most key facts come from statements by City of Calgary and Michael Thompson, as reported by 3 news outlets. Outlets repeating the same statements do not confirm them independently. |
8 key facts · 0 independently corroborated · 8 from statements or releases · none disputed